Further developments made at UCR site

[vc_row][vc_column][vc_column_text]As you can see from the photos, the development of UCR is coming along well and we have further progress to report. The foundations are now complete, nearly all the retaining walls are done, steel work is 85% complete on area 1 and stair 2 is installed.

Over the next two weeks we will see steelwork start on area 2, the contractors will start to cast the upper floor slabs and drainage works will commence.

[/vc_column_text][us_image_slider ids=”6029,6028,6026,6025″ fullscreen=”1″][/vc_column][/vc_row]